UPDATE FROM WITHYHEDGE LANDFILL SITE : 20 SEPT 2024

As construction on the newest area of tipping at the Withyhedge Landfill site continues, Cell 9, RML are pleased to provide the following update:

 

Cell 9A

Work on this sub-cell has been completed in accordance with CQA requirements. The Cell 9A CQA Validation report was submitted to NRW on 02-09-24. This is currently being reviewed by the regulator, NRW. You can see their latest update here – Natural Resources Wales / Natural Resources Wales reviews engineering report on new Withyhedge Landfill cell construction9A

NRW will need to approve this before RML commence tipping in Cell 9.

 

Cell 9B

The work on this sub-cell has been completed in accordance with CQA requirements. A CQA report is currently being prepared to submit to the regulator, NRW, for approval. We anticipate it will be submitted by next week.

 

Cell 9C

Shaping work has been completed. Lining works are currently in progress. As with the other Cells, all work is being done in accordance with CQA requirements.

RML will provide further updates as we progress.

 

Picture taken 17.9.2024