WITHYHEDGE LANDFILL SITE REOPENING UPDATE
Resources Management (UK) Ltd. are pleased to announce that the Withyhedge site will reopen from Thursday 2nd January for the acceptance of pre-qualifying materials only, with a view to fully reopening the site to third party customers in the following weeks once further measures have been implemented.
During the period of site closure, RML have completed extensive air quality and waste sampling & analysis, geotechnical and regulatory consultation, comprehensive engineering work, and the installation of improved gas management equipment and technology; In addition, the re-opening of the site will coincide with the implementation of stricter waste acceptance procedures.
RML are satisfied that the historical issues are now fully resolved, and that the completion of this work will provide a high level of protection for both the site and its neighbouring communities going forward.
RML also acknowledge the concerns raised by the communities, and can confirm that alternative arrangements have been made, where possible, for the overnight parking of vehicles away from the local laybys
CONSTRUCTION OF CELL 9 UPDATE
UPDATE FROM WITHYHEDGE LANDFILL SITE : 20 SEPT 2024
As construction on the newest area of tipping at the Withyhedge Landfill site continues, Cell 9, RML are pleased to provide the following update:
Cell 9A
Work on this sub-cell has been completed in accordance with CQA requirements. The Cell 9A CQA Validation report was submitted to NRW on 02-09-24. This is currently being reviewed by the regulator, NRW. You can see their latest update here - Natural Resources Wales / Natural Resources Wales reviews engineering report on new Withyhedge Landfill cell construction9A
NRW will need to approve this before RML commence tipping in Cell 9.
Cell 9B
The work on this sub-cell has been completed in accordance with CQA requirements. A CQA report is currently being prepared to submit to the regulator, NRW, for approval. We anticipate it will be submitted by next week.
Cell 9C
Shaping work has been completed. Lining works are currently in progress. As with the other Cells, all work is being done in accordance with CQA requirements.
RML will provide further updates as we progress.
COMMUNITY TECHNICAL GROUP UPDATE
Landfill Site Technical Specialists meet with Community Technical Group
RML were pleased to host the technical meeting on Wednesday 4th September, between our technical specialists Geotechnology Ltd and the Community Technical Group. The meeting provided an opportunity for the specialists to provide the community on several subjects, which included:
- Overview of Withyhedge Landfill Site – Propeller System
- Odour and Gas Monitoring Infrastructure – Community and Site
- Review of Monitoring Results to Date
- Rudbaxton Monitoring and Proposed Future Monitoring
- Site Walkover
- Discussion about future engagement, liaison and data sharing
Thanks to Geotechnology Ltd and the Community for coming together.
If you would like to stay up to date with news and updates from RML (Withyhedge Landfill Site), please provide your email address to receive notifications and updates via email.
NRW WATER SURFACE MONITORING REPORT
Statement on NRW Water Surface Monitoring
We welcome the recent report from Natural Resources Wales (NRW) regarding water surface monitoring. Ref: CAR_NRW0044753
The data confirms that there are elevated levels of pollution emanating from upstream to the landfill site, however, the water quality at RMLs discharge point is below the permit threshold; this in turn is positively contributing towards improved water quality downstream.
We will continue working closely with NRW and other stakeholders to ensure we are maintaining high standards of water quality, within our permit stipulations and or the long-term protection of our streams and water courses.
LANDFILL CONSTRUCTION "CELL 9" UPDATE
As an update to the development and construction of Cell 9, the next section of landfill space to be created at site; Cell 9 will be split into 3 smaller sub-cells: 9a, 9b and 9c.
We can confirm that:
Cell 9a
The work on this subcell has been completed and constructed in accordance with construction quality assurance (CQA) requirements. A CQA report is currently being prepared to submit to the regulator, NRW, for approval.
Cell 9b
The cell has been prepared and lined. The next phase is to lay the drainage blanket and works to complete this will continue over the next few weeks. As with Cell 9a, all work has been done in accordance with CQA requirements.
Cell 9c
Initial shaping has commenced, and construction will continue through the Summer.
We will provide further updates as we progress.
SURFACE WATER LAGOON IMPROVEMENTS
Week commencing 1st July, RML began work on site to build new surface water lagoons. The construction of these lagoons is an integral part of upgrading our surface water management infrastructure as the impermeable layers of the site expands. The purpose of the lagoons is to protect the environment by capturing and treating surface water run off before it gets discharged. Providing surface water ponds at this location is a Permit requirement. Leachate is collected separately and removed from site by tanker to a treatment works so these ponds will not receive any leachate.
Various teams from Natural Resources Wales (NRW) including the Industry Regulation team, Local Environment Team, and Forestry Regulation Team have recently visited this area. All developments and improvements to this particular area of site continue to be carried in consultation with the regulator and within the site's permitted compliance.
Moving forward, RML will continue to work closely with the regulator as NRW themselves continue to closely monitor this area of the site whilst work takes place.
MAIN FLARE MAINTENANCE : 30TH JULY
29th July 2024
This is an announcement to confirm that Resources Management UK Limited will be undertaking an annual maintenance of the main landfill gas flare on Tuesday, 30th July.
The work will commence at 9 AM and should not take more than 3 hours.
While we do not expect any disruption of landfill gas release, there is always the potential for such an event during such maintenance.
SITE UPDATE STATEMENT : 23 JULY 2024
Natural Resources Wales released a statement on Friday 19th July confirming that all work required from our site as part of their Regulation 36 Enforcement Notices served on RML in February and April of this year, has been fully complied with.
The continued work has resulted in the dissipation of landfill odour, and we anticipate this will continue to be the case going forward, notwithstanding the presence of other odour sources not related to Withyhedge Landfill Site in the vicinity.
We continue to work closely with the regulator and continue engineering work on the next cells, and work on improving and updating the gas management infrastructure on site. The site will remain closed until this work is completed.
WITHYHEDGE LANDFILL SITE UPDATE : 5 JULY 2024
SCHEDULED MAINTENANCE ON MONDAY 8TH JULY
On Monday 8th July, scheduled maintenance on the gas collection systems will be carried out, we expect this will take a few hours. The backup flare will be running, and we don’t anticipate this work will cause any odour issues but would like to keep the community informed that this work will be taking place.
Moving forward, RML will endeavour to provide updates whenever such work is scheduled.
WITHYHEDGE LANDFILL SITE UPDATE : 28 JUNE 2024
RML are pleased to confirm that progress on the construction of cell 9 is progressing to schedule and that the CQA for its approval is due to be submitted to the regulator imminently.
We will also be taking advantage of the extended site closure period to update our gas management equipment on site; this will enable the site to be more resilient to breakdowns and give increased capacity and efficiency to the gas collection network.
RML have consistently taken the lead in initiating air quality monitoring around the site and welcome the efforts currently being undertaken by PCC and NRW. To further support this ongoing initiative and the work of the independent specialist consultants already employed, RML will permanently introduce AQ Mesh monitors on-site. These new sensors, designed to continuously detect hydrogen sulfide and other VOC gases, will be placed at various locations around the site, with the information being shared with our partners.
We continue to work closely with NRW and will provide further updates on progress and re-opening dates when they are known.